WAG Plus 600
Project |
| WAG Plus 600 |
Client |
| OMV AG, Austria |
Country |
| Austria |
Time frame |
| 2005 - 2011 |
Engineering and management services to increase the capacity of the existing West Austria Gas Pipeline system by 600,000 Nm³/h to 1,800,000 Nm³/h max. capacity by looping and boosting.
Technical Data:
- Installation of approx. 80 km, 48" loop lines
- 4 gas turbine driven turbo compressors:
- (3 x 12MW ISO and 1 x 15MW ISO)
- 2 electrically driven turbo compressors
- (2 x 8 MW integrated high-speed electric motor compressor units)
- 1 gas dehydration facility
Highlights:
- Quick project handling in the first phase
- Very detailed environmental impact studies for the loop sections
- Expansion of existing stations with minimum downtime for tie-ins
- Extremely quiet compressor station that blends into the rural landscape