1967
Pius Lässer establishes engineering office in Innsbruck (AUT)
1967
1967
1967
First oil and gas contracts for Transalpine “TAL” Crude Oil Pipeline (ITA, AUT and GER), expansion of tank farms in Ingolstadt and Trieste
1967
1967
First water contract for Dornbirn Wastewater Treatment Plant (AUT)
1969
1969
Adolf Feizlmayr joins the company to form ILF partnership, office in Munich is opened (GER)
1971
1971
Contract for expansion of Transalpine “TAL” Pipeline
1972
1972
Contract for Arlberg Road Tunnel (AUT), 14 km
1974
1974
Contract for Grafendorf Compressor Station (AUT), throughput: 1.3 million Nm³, 42–52 bar
1974
1974
Contract for Iraq–Turkey Pipeline from Kirkuk to Iskenderun (IRQ, TUR), 1,000 km
1976
1976
Contract for Voigtei–Barenburg Liquid Sulphur Pipeline (GER)
1976
1976
Contract for Bauchi Commercial Vehicle Plant (NGR)
1977
1977
Contract for Riyadh Water Transmission System from Jubail to Riyadh (KSA), 500 km,
830,000 m³/d
New office in Riyadh (KSA)
Contract for Brenner Base Tunnel (AUT, ITA)
1980
1980
Contract for Hannover–Würzburg High-Speed Railway Line (GER)
1981
1981
New office in Lagos (NGR)
1982
1982
Contract for Jubail–Riyadh Water Transmission System, Line C (KSA),
386 km, 380,000 m³/d
1982
1982
Use of ILF drilling equipment for AFRO pipeline route investigation (ITA, AUT, GER)
1985
1985
Contract for Etzel Gas Storage Project (GER), 3,200 million Nm³
Contract for Tafna–Oran Water Transmission System (ALG), 115 km, 250,000 m³/d
1986
1986
New office in Washington DC (USA)
1986
1986
Contracts for Cheurfas II and Fontaine de Gazelle Dams (ALG), 82.4 m high gravity dam, 56 m high earth-fill dam
1988
1988
Contract for UK Crossover Cavern of the Channel Tunnel (GBR)
1990
1990
New office in Linz (AUT)
Contract for Mannesmann Mobilfunk D2 Mobile Network (GER), with partners
1991
1991
Contract for Ebensfeld–Erfurt High-Speed Railway Line (GER), 107 km
1992
1992
New offices in Prague (CZE) and Milan (ITA)
Contract for Yanbu–Madinah Water Transmission System from the Red Sea to Madinah (KSA), 366 km, 350,000 m³/d
1993
1993
Founding of ILF Switzerland
1994 and 1995
1994 and 1995
Contract for Gotthard Base Tunnel (SUI), 57 km
Contract for SS 22 Bolzano–Leifers Bypass Road (ITA)
1996
1996
Contract for Cologne–Frankfurt High-Speed Railway Line (GER), 219 km
New offices in Bratislava (SVK) and Vienna (AUT)
1998
1998
Contract for Circe Fiber Loop 2, Fiber-Optic Cable Network (GER), 1,100 km
New offices in Warsaw (POL) and in Moscow (RUS)
1999
1999
Contract for Sohar–Salalah Gas Pipeline (OMN), 300 km, 32 and
700 km, 24″
2000
2000
New office in Ploiesti (ROU)
Contract for Fujairah Water Transmission System (UAE),
2 × 64″, 180 km,
2 × 24″, 19 km
2001
2001
Contract for Baku–Tbilisi–Ceyhan “BTC” Pipeline (TUR)
New office in Ankara (TUR)
2002
2002
New office in Abu Dhabi (UAE)
Contract for Sulaibiya Wastewater and Reclamation Plant (KWT)
Contract for Baltic Beta Offshore Compressor Station (POL), 100,000 Nm³/d, 130 bar
2003
2003
Adolf Feizlmayr awarded an honorary doctorate (Dr. h.c.) from the Montanuniversität Leoben (AUT)
ILF has over 600 employees
New office in Baku (AZE)
2004 and 2005
2004 and 2005
New offices in Beijing (CHN), Lahore (PAK) and Almaty (KAZ)
Contract for SNOx Reduction Plant (AUT)
Contract for Leipzig/Halle Airport (GER)
Acquisition of shares in Airport Consulting Partners GmbH, Stuttgart (GER)
2006
2006
Acquisition of TECON Engineering GmbH (AUT)
Contract for Shahdag Tourism Complex (AZE)
Contract for Czajka Wastewater Treatment Plant (POL)
Contract for Shuqaiq Independent Water and Power Project (KSA)
2007
2007
ILF has over 1,000 employees
New office in Salzburg (AUT)
Contract for Habshan–Fujairah Crude Oil Pipeline (UAE)
Adolf Feizlmayr and Pius Lässer join the Advisory Board
2008
2008
Contract for Metro Warsaw, Line 2 (POL)
New office in Graz (AUT)
Contract for Eskene–Kuryk Oil Pipeline (KAZ)
2010
2010
Contract for Fujairah Desalination Plant (UAE)
Contract for Gasunie Compressor Stations (GER)
Contract for Atdorf Pumped Storage Plant (GER), 1,400 MW
2012
2012
Contract for TANAP Pipeline (TUR), 1,815 km, 56/48″
Contract for Tbilisi Bypass Rail Project (GEO)
Contract for Mohammed bin Rashid Al Maktoum Solar Park (UAE)
New office in Tbilisi (GEO)
2013
2013
New offices in Erbil (KRI), Santiago (CHI) and Calgary (CAN)
Contract for Samotlor Oil Field Redevelopment (RUS)
Contract for Kozienice Power Plant (POL), 1,075 MW
2014
2014
Contract for Common Seawater Supply Project (IRQ), 435 km, 2 million m³/day, FEED services for seawater pipeline system for enhanced oil recovery “EOR”
New office in Stathelle (NOR)
2015
2015
Contract for Muzizi Hydropower Plant (UGA)
Acquistion of INFRA Project Development GmbH
New offices in Bogota (COL) and Bangkok (THA)
2016
2016
ONE ILF initiative launched
ILF has over 2,000 employees
2016
2016
New office in Mumbai (IND)
2016
2016
Contract for TAP Gas Pipeline (ALB, GRE), 188 km and 215 km, 48″
Contract for SuedLink HVDC Cable Connection (GER), 1,000 km
2016
2016
Acquisition of EUT Engineering
2017
2017
ILF celebrates 50 years of Engineering Excellence worldwide
2017
2017
Contract for TAPI Gas Pipeline (PAK, AFG), 1,625 km, 56″
2017
2017
Release of ILF’s image film
2017
2017
Contract for the Mohammed bin Rashid Al Maktoum Solar Park, Phase 3 (UAE), 5,000 MW, 6.5 million tons of CO2 reduction per year
2018
2018
Contract for Taimeralm Energy Recovery Station (AUT), world’s first crude oil pipeline power plant
Contract for Al Moghamass Strategic Tanks (KSA), 12 million m³
Contract for Metro Warsaw Line 2 (POL), Expansion West and North-East
2018
2018
Contract for Rabigh – Jeddah – Makkah Water Transmission System and Jubail – Riyadh Water Transmission System Phase 3 (KSA), >1,000 km in total
2018
2018
Contract for Großinzersdorf Wind Farm (AUT), 9.9 MW
Contrat for Ajaokuta – Kaduna – Kano Gas Pipeline (NGR), PMC
2018
2018
Contract for Nam E-Moun Hydropower Project (LAO), 129 MW
Contract for SuedLink HVDC Cable Connection (GER), 1,200 km
Contract for Gotthard Road Tunnel, 2nd tube (SUI)
2019
2019
Contract for 2nd Munich S-Bahn Main Line (GER), > 10 km in total, Design and PMC
2019
2019
Master Service Agreement for Tengiz Oil Field (KAZ), 26 billion barrels
New office in Atyrau (KAZ)
2019
2019
Contract for Al-Basrah Seawater Desalination Project (IRQ), 1,000,000 m³/d
2019
2019
Contract for Red Sea Project – sustainable energy storage concept for tourism resort (KSA), Technical advisory services
Contract for Demo4Grid Hydrogen Project – H2 Electrolyzer Facility (AUT), Owner’s engineering services
2020
2020
Uninterrupted services in spite of the global Covid-19 pandemic
ILF has over 2,500 employees
2020
2020
ILF commits to the UN’s 17 Sustainable Development Goals “SDGs”
2020
2020
Contract for SuedLink HVDC Cable Connection, lots 1, 7, 8, 9 (GER), Engineering services
Contract for ammonia storage tank incl. loading and unloading facilities, Aqaba (JOR), PMC
2020
2020
Contract for Gaildorf Green Energy Storage Facility Pilot Project – wind power combined with pumped storage (GER), Engineering services
Contract for Baltica 2 and 3 Offshore Offshore Windfarm (POL), Engineering services
2021
2021
Contract for Amaala Project – high end multi-utility tourism development (KSA) aiming fo ran operational zero carbon footprint, Technical advisory services
2021
2021
Contract for Endikat Hydropower Project (IND), Owner’s engineering services
Contract for expansion of Wastewater Treatment Plant Frankfurt (GER), Engineering services
2021
2021
Contract for Dresden-Prague High-Speed Railway Line (GER-CZE), Engineering services
Frame Contract for Wafra Oilfield, CO2 emission reduction (KWT), Owner’s engineering services and PMC
2021
2021
Contract for Metro Warsaw, Line&nbs;3 (POL), Engineering services
Contract for Green Riyadh – urban greening project, (KSA), PMC