Hydropower Plant inauguration on the Weerbach (AUT)

more

The Gemeinschaftskraftwerk Weerbach (GKW) Hydropower Plant was inaugurated at the end of June.
​​​​The GKW Hydropower Plant uses the natural hydraulic power of the Weerbach stream. Water is fed via a water intake structure, located at around 1,500 masl, and an approximately 4-km-long penstock, to the power house, located at around 1,100 masl. At the power house, a Pelton turbine with a capacity of 1.7 MW generates around 7.5 gigawatt hours of electricity per year, which is fed into two grids via a 25 kV and/or 10 kV transmission line.

After flowing through the turbine, the water is fed into the intake of the downstream hydropower plant, where it is used once again to generate electricity. A second option would be to discharge the water leaving the turbine directly into the Weerbach stream so that the GKW Hydropower Plant can also be operated independently of the existing downstream hydropower plant.

In the residual flow section at the GKW Hydropower Plant, discharge into the Weerbach stream is varied as ecological flow to ensure compliance with ecological requirements and to maintain the hydrological and environmental balance in accordance with the granted permit.

The short construction period of around one year is remarkable and was only possible thanks to the extremely cooperative relationship between all those involved.
We are proud to have been able to successfully complete our work on this complex project, and warmly congratulate all those involved.

Shown in the photo, from right to left, in front of the new Pelton turbine: H. Eller (Client: Elektrogenossenschaft Weerberg) E. Söllner (Lawyer – Legal Representative) G. Haim (Client: Kraftwerk Haim KG) S. Ploner (Energy Economist / Client’s Technical Advisor) R. Fritzer (ILF, Designer) M. Schwarzkopf (ILF, Designer)