collage_HGF_rev3_2018-1

Expansion of wastewater treatment plant Frankfurt/Main (GER)

more

The Stadtentwässerung Frankfurt am Main (SEF, https://www.stadtentwaesserung-frankfurt.de/) entrusted ILF Consulting Engineers together with a German partner to plan, execute and implement the expansion of the Niederrad Wastewater Treatment Plant (WWTP).

The Niederrad WWTP is currently reaching its maximum design capacity of 1.35 million PE. The expansion is therefore urgently required in order to be prepared for future developments in the constantly growing Frankfurt area. For this reason, the number of secondary aeration tanks (with a volumetric capacity of 7,200 m3 each) will be increased from 8 to 10, and the number of secondary sedimentation tanks (with a volumetric capacity of 1,875 m3 each) will be increased from 32 to 40. The project comprises the smooth integration of these new tanks, as well as the associated mechanical, electrical and SCADA equipment, into the existing plant while maintaining continuous plant operation and compliance with effluent requirements.

Additionally part of the assignment are the re-routing of existing pipework and the construction of an access road.

ILF will be involved in all eight service phases of this project, which are in accordance with the German Official Scale of Fees for Services by Architects and Engineers (HOAI), including the building permission application as well as construction supervision and commissioning. The completion is scheduled for February 2027.

Site map of the Niederrad WWTP with the areas of secondary treatment expansion highlighted in color. (Source: SEF Tender Documents)